Project PlanningAdvanced Non-LWR

Texas A&M-RELLIS Energy Proving Ground

πŸ“ TX
Capacity
β€”
Expected Operation
β€”
Reactor Type
Multiple: Kairos KP-FHR, Natura MSR-100, Terrestrial IMSR, Aalo Pod
Regulatory Status
NRC pre-application for an Early Site Permit (Part 52); ESP application not yet submitted as of NRC page update 2026-09-15 (earlier targets Q4 2025, then May 2026, passed); four developers selected 2025-02

Details

Primary Use
Demonstration / research

Research detail Β· verified 2026-10-10

Stage
Early stage (site agreement or plan only)
Commercial power
No (test, research, military or demonstration)
NRC docket
Pre-application project 99902136
Stated target operation
Initial phases early-to-mid 2030s (Texas A&M/NRC pre-application materials); Natura stated MSR-100 deployment by 2029 at RELLIS
Key dates
2024-11-07 Texas A&M letter of intent to NRC for ESP; 2025-02-04 four developers selected; 2026-06-23 Terrestrial Energy 77-acre ground lease signed (see separate row)
Not verified / conflicts
ESP submission target slipped (NRC page says Q4 2025; search results cite May 2026); no submission found as of 2026-10-10. 'Early-to-mid 2030s' attribution came from search summary of the NOI/NRC page, not read verbatim. Kairos, Natura and Aalo agreements are agreements to explore siting; only Terrestrial has a signed ground lease. Last Energy PWR-5 pilot at RELLIS is a DOE Reactor Pilot Program project (excluded). Merge note: project_type set to advanced reactor; the ESP is meant to host several developers (Kairos, Natura, Terrestrial, Aalo) with mixed designs.