Under ConstructionOther / Unclassified

RELLIS Pilot

πŸ“ Bryan, TX (Brazos County Co.)Developer: Last EnergyVendor / Tech: Last Energy
Capacity
5 MW
Expected Operation
2026
Reactor Type
Last Energy PWR-5
Regulatory Status
DOE approved the final Documented Safety Analysis 2026-10-08, moving the project to readiness review, the last step before authorization for criticality and operations. Facility built; full LEU core procured. Company says it plans criticality in October 2026.

Details

Primary Use
Research / demonstration
Grid Connection
ERCOT
Construction Start
2026

Research detail Β· verified 2026-10-10

Stage
Under construction
Commercial power
No (test, research, military or demonstration)
Stated target operation
Criticality planned in October 2026 (stated by Last Energy, per WNN 2026-10-08 coverage)
Key dates
2025-08-12 selected for DOE Reactor Pilot Program; 2025-10 partnership/land lease with Texas A&M System announced; 2026-01 groundbreaking (KBTX); 2026-05 PDSA approved by DOE; 2026-10-08 DSA approved
Workforce
Texas A&M says this would be the first reactor on a university campus in over 30 years; no specific training partnership or job numbers found.
Not verified / conflicts
Missed the July 4, 2026 goal. As of 2026-10-10 no criticality announcement found. Partnership announcement date: WNN says 2025-10-15; the TAMUS story page I opened showed a later date β€” exact date of the lease signing not confirmed.

Key Organizations

Developer
Last Energy

Power Purchase Agreements1 PPA

Texas A&M RELLIS Campus
announced
State Policy Context
View nuclear-related legislation and energy stats for Texas
TX Policy β†’