NRC ReviewOther / Unclassified

Port of Victoria

📍 Victoria, TXDeveloper: Blue EnergyVendor / Tech: Blue Energy
Capacity
1,500 MW
Expected Operation
2028
Reactor Type
BWRX-300 / GE Vernova Hitachi Nuclear Energy
Regulatory Status
Part 1 of a phased NRC construction permit application, including a limited work authorization request, received by NRC (notice of receipt 2026-10-08); Part 2 expected 2027 after one year of site data collection

Details

Primary Use
Power generation / industrial
Construction Start
2028

Research detail · verified 2026-10-10

Stage
Application under NRC review
Commercial power
Yes
NRC docket
Project No. 99902137 (NRC-2026-4654)
Stated target operation
Nuclear power from 2032; gas turbines 2030 (stated by Blue Energy/GE Vernova, 2026-05)
Stated operations jobs
Approximately 100 permanent jobs in first phase (Port of Victoria/Blue Energy, 2025-10-14)
Key dates
2025-12 NRC approved Blue Energy licensing topical report; 2026-04 project acceleration agreement with GE Vernova Hitachi; 2026-09-15 Part 1 CP application + LWA request filed (per NRC); 2026-10-08 NRC Federal Register notice of receipt; 2027 final investment decision expected and Part 2 of application expected (2H 2027) (per Blue Energy)
Not verified / conflicts
Filing date conflict: NRC Federal Register notice says filed 2026-09-15; Blue Energy, GE Vernova and ANS say 2026-09-16. Unit count conflict: NRC notice describes a single-unit BWRX-300 plant; ANS (2026-10-09) says five BWRX-300s (~1.5 GW) targeted online in 2032 - not confirmed by a Blue Energy primary source, so not recorded as a stated target. Blue Energy CEO says the company aims for 'power in 48 months or less' (company goal, not a project-specific date). Nuclear output will serve nearby data centers per ANS. No job numbers found.

About

1.5 GW

Key Organizations

Developer
Blue Energy
State Policy Context
View nuclear-related legislation and energy stats for Texas
TX Policy →