NRC ReviewSMR (LWR)

Palisades SMRs

📍 Covert, MI (Van Buren County Co.)Developer: Holtec InternationalVendor / Tech: Holtec International
Capacity
600 MW
Expected Operation
2030+
Reactor Type
SMR-300 (PWR)
Regulatory Status
Part 1 of phased construction permit application (with limited work authorization request) docketed 2026-02-13; NRC environmental impact statement scoping began 2026-06-15; NRC granted exemption 2026-08-28 allowing early site work (support-of-excavation and cutoff walls) before LWA; Part 2 due by mid-2027.

Details

Primary Use
Power generation
Grid Connection
MISO
Fuel Type
LEU
Construction Start
2026

Research detail · verified 2026-10-10

Stage
Application under NRC review
Commercial power
Yes
NRC docket
50-616, 50-617 (NRC-2026-0265)
Stated target operation
Unit 1 2030, Unit 2 2031 (Holtec presentation, Sept 2025); 'early 2030s' (Holtec as reported by ANS 2026-04-02 and Neutron Bytes 2026-01-11)
Stated construction jobs
4,000+ personnel during construction of the dual-unit plant (Holtec presentation, Sept 2025)
Stated operations jobs
280 direct long-term jobs plus supply chain (Holtec presentation, Sept 2025)
Key dates
2025-02 Holtec 'Mission 2030' launched; 2025-12-02 DOE selected project for Gen III+ SMR Tier 1 First Mover award (~$400M, subject to negotiation); 2025-12-31 CP application Part 1 submitted; 2026-02-13 NRC found Part 1 acceptable for docketing; 2026-06-15 EIS notice of intent / scoping; 2026-08-28 NRC exemption for early site work; Holtec requested NRC approval of Part 1 by 2026-12-31; Part 2 due mid-2027
Workforce
Holtec says the SMR-300 project will build on the workforce assembled for the Palisades restart (Holtec presentation, Sept 2025). Hyundai E&C alliance to build the Palisades project and a 10 GW SMR-300 fleet.
Not verified / conflicts
This is an SMR, included here because the caller assigned it to this scope; de-duplicate against the SMR list. Target date conflict: Holtec's Sept 2025 slides say 2030/2031; 2026 reporting says 'early 2030s'. DOE award: Holtec S-1 says ~$400M expected but terms not final; an ANS tag-page summary mentioned a $94M DOE award in May 2026 that I could not confirm. A search-result summary quoted '2,000 personnel during construction', but the Holtec slide itself says 4,000+; the slide figure is used.

About

Two 300 MW SMRs co-located at Palisades site. Construction permit application targeted 2026.

Key Organizations

Developer
Holtec International

Federal Funding

DOE
DOE Funding ·
DOE LPO $800M (Generation III SMR program)
—
awarded
State Policy Context
View nuclear-related legislation and energy stats for Michigan
MI Policy →