Project PlanningLarge LWR

V.C. Summer Units 2 and 3 completion

πŸ“ SC
Capacity
β€”
Expected Operation
β€”
Reactor Type
Westinghouse AP1000
Regulatory Status
Pre-FID development. Santee Cooper-Brookfield MOU signed December 2025; Brookfield submitted its first feasibility deliverables on the 2026-06-26 deadline; Brookfield final investment decision due by 2028-03-31. The earlier NRC combined licenses were terminated in 2019, so new NRC licensing is needed.

Details

Primary Use
Power generation

Research detail Β· verified 2026-10-10

Stage
Site and developer chosen
Commercial power
Yes
Key dates
2017-07 original construction abandoned; 2019-03-06 NRC terminated COLs NPF-93/NPF-94; 2025-10 Santee Cooper selected Brookfield; 2025-12-10 MOU signed; 2026-05 Brookfield-The Nuclear Company JV formed; 2026-06-26 initial feasibility deadline; by 2026-12-31 federal loan application; by 2027-02-28 operator selection; by end of 2027 cost and schedule analysis; by 2028-03-31 FID
Workforce
Santee Cooper says the project would create 'thousands of temporary construction jobs and hundreds of permanent operational jobs' (no figures; ANS 2025-12-10, WNN 2025-10-27). The MOU requires Brookfield to draft an economic development plan covering use of South Carolina companies and labor, K-12 and higher-education partnerships, and workforce development (SC Daily Gazette; see unverified_notes). University of South Carolina and Westinghouse signed an AP1000 workforce development agreement 2026-09-29 for a planned USC Nuclear Innovation Center; USC plans to request $100M from the state legislature (WRDW 2026-09-30).
Not verified / conflicts
Site town/county (Jenkinsville, Fairfield County) is from the caller's candidate list and is the long-established V.C. Summer location; no page opened in this session stated it. Economic development plan terms come from a search-result snippet; the SC Daily Gazette and WLTX pages returned 403. The 2019 COL termination date comes from search-result snippets of an NRC letter and the 2019-03-13 Federal Register notice; the notice page itself was not opened. No completion date has been stated by Santee Cooper or Brookfield. The USC-Westinghouse agreement covers AP1000 fleet deployment in general and is not specific to V.C. Summer; per WRDW it commits Westinghouse to no investment.