Under ConstructionMicroreactor

Radiant Kaleidos Demonstration Unit in INL DOME

πŸ“ IDDeveloper: Radiant Industries
Capacity
1 MW
Expected Operation
β€”
Reactor Type
Radiant Kaleidos
Regulatory Status
DOE approved PDSA Feb 2026; first fuel tranche received 2026-07-01; reactor left El Segundo, CA for the INL DOME on 2026-08-12. Five-phase test program (zero-power criticality through 150-hour full-power run) was targeted for Q3 2026; no criticality announcement found as of 2026-10-10.

Details

Primary Use
Demonstration / research

Research detail Β· verified 2026-10-10

Stage
Under construction
Commercial power
No (test, research, military or demonstration)
Stated target operation
Test campaign targeted to conclude in Q3 2026 (Radiant, per NEI Magazine 2026-08-21) β€” not met per available sources
Key dates
2025-08-12 selected for DOE Reactor Pilot Program; 2026-02 PDSA approved; 2026-07-01 first fuel tranche received; 2026-08-12 shipped to INL DOME; 2026-09-17 passive cooldown test completed (Radiant)
Workforce
Radiant building R-50 reactor factory on an 80-acre Oak Ridge, TN site (factory, not a reactor site). Radiant also selected for Buckley SFB (Air Force ANPI) and Fort Benning (Army Janus) β€” separate rows.
Not verified / conflicts
radiantnuclear.com returned 403. Criticality status after mid-Sept 2026 unconfirmed; one search summary said no criticality announcement as of end of Q3 2026. Passive cooldown test (2026-09-17) from Radiant newswire release found in search; full text not opened.