NRC ReviewSMR (LWR)
Project website β†’

Belews Creek SMR

πŸ“ Walnut Cove, NC (Stokes County Co.)Developer: Duke Energy
Capacity
β€”
Expected Operation
2034
Reactor Type
SMR
Regulatory Status
ESP application docketed and under NRC review; NRC uncontested (mandatory) hearing held 2026-09-17 in Danbury NC, record open to 2026-10-01; EIS scoping begun 2026-04; no decision to build

Details

Primary Use
Power generation
Grid Connection
PJM / SERC
Construction Start
2030+

Research detail Β· verified 2026-10-10

Stage
Application under NRC review
Commercial power
Yes
NRC docket
52-055
Stated target operation
First SMR online 2036; 600 MW of advanced nuclear by 2037 (stated by Duke Energy, 2025-12-30 ESP press release)
Key dates
2025-12-30 ESP application submitted; 2026-01-07 NRC notice of receipt; 2026-02-09 NRC accepted and docketed application, hearing opportunity noticed; 2026-04-10 hearing request deadline; 2026-04-27 NRC notice of intent to prepare EIS (Army Corps cooperating); 2026-09-17 NRC mandatory hearing, Danbury NC
Not verified / conflicts
NRC review is expected to run to about May 2027 (NRC page via search summary only); no ESP issuance found as of 2026-10-10. Duke's 2026 resource-plan discussion (FITSNews 2026-09-28) says the first ~1,100-1,200 MW around 2037 will come from either Belews Creek SMRs (up to six) or a large LWR at W.S. Lee (Cherokee County SC) - technology not selected. Duke spokesperson said the plant 'will create jobs' but gave no numbers. No college/union partnerships tied to the project found.

About

First modular reactor targeted by 2034.

Key Organizations

Developer
Duke Energy
State Policy Context
View nuclear-related legislation and energy stats for North Carolina
NC Policy β†’