US·Regulatory Docket·NRC

Docket Nos. 50-325 and 50-324

Closed

Duke Energy Progress, LLC; Brunswick Steam Electric Plant, Units 1 and 2

Filed 2021-11-30Last update 2021-11-30

Summary

The U.S. Nuclear Regulatory Commission (NRC, the Commission) is issuing an exemption in response to a request from Duke Energy Progress, LLC (Duke Energy, the facility licensee), on behalf of an individual named in the request, dated July 29, 2021, as supplemented by letters dated August 26, 2021 and October 25, 2021. The exemption permits a waiver of examination and test requirements for that individual to be supported by extensive actual operating experience at a comparable facility that occurred greater than 2 years before the date of application, as opposed to the regulatory requirement that this experience be within 2 years. The exemption is effective upon issuance, but only applies to the specifically named individual.