Nuclear Development, LLC; Tennessee Valley Authority; Bellefonte Nuclear Plant, Units 1 and 2; Construction Permit Transfer Application; Withdrawal by Applicant

Filed 2023-10-13Last update 2023-10-13

Summary

The U.S. Nuclear Regulatory Commission (NRC) has granted the request of Nuclear Development, LLC (ND) to withdraw its application, dated November 13, 2018, to transfer the construction permits (CPs) for Bellefonte Nuclear Plant (BLN), Units 1 and 2 (Construction Permit Nos. CPPR-122 and CPPR-123, respectively). ND had requested that the NRC consent to the transfer of the BLN CPs from Tennessee Valley Authority (TVA) to ND. The CPs for BLN, Units 1 and 2, expired on October 1, 2021.